Kingfisher / B&Q Data Centre Completed

05 October, 2016

Kingfisher / B&Q Data Centre Completed

ITE have completed the second phase of the Kingfisher / B&Q data centre cooling upgrade.

The work entailed the replacement of 8 redundant air handling units with their associated condensers and replacing them with new efficient inverter controlled units from Denco.

The work was carried out within a live data hall environment with no down time required during the installation.

In order to maintain a sufficient level of cooling the work was carried out in 4 phases.

The units in data hall 1 have been running since 2015 and the client has already reported a considerable cost saving in running costs.